PROJECT DETAILS
Client: Blackpool Teaching Hospitals (NHS Foundation Trust)
Facilities:
- Parkinsons Disease Clinic
- Speech Therapy Clinic
- X-Ray Department
- Dermatology Clinic
- Rheumatology Clinic
- Outpatients department with four fully equipped rooms
![](https://www.eurositepower.co.uk/wp-content/uploads/2023/01/Clifton-Hospital-Tonnes.png)
Gross CO2 saved from May ’14 to Mar ’22
![](https://www.eurositepower.co.uk/wp-content/uploads/2023/01/Clifton-Hospital-Savings.png)
Energy saving from May ’14 to Mar ’22
![](https://www.eurositepower.co.uk/wp-content/uploads/2023/01/Clifton-Hospital-Elec.png)
Electricity generated from August ’16 to Mar ’22
![](https://www.eurositepower.co.uk/wp-content/uploads/2023/01/Clifton-Hospital-Heat.png)
Heat generation from August ’16 to Mar ’22
GOALS
Reduce energy and CRC costs
Electricity – lighting and power for public areas, bedrooms, and hotel facilities
Heat – hot water production for space heating and leisure facilities
Air conditioning systems – used to keep rooms and whole complex cool
CHALLENGES
Wide range of facilities operating 24/7
Remove the old CHP unit while plant should have been kept operational throughout the installation
New CHP had to be setup to operate correctly alongside the hospitals stand-by generator
Installation had to be live tested before the handover
SOLUTIONS
Implemented: On-Site Utility Solution
Implemented: “EuroSite Power On-Site Utility Solution”
Inverter equipped CHP technology allows output to match demand and maintain efficiency
Integrated CHP and stand-by generator control
Installed: 100 kilowatt Combined Heat and Power (CHP)